The trouble with FOM/WDG interconnection
The current interconnection process presents a significant problem that must be fixed if we are to unleash the FOM market segment — the market segment that Germany targeted, propelling the country to become a global clean energy leader.
Because of the uncertainty and extra costs of interconnecting an FOM project in California, many projects never get off the ground, and many more are never even considered.
Compared to the process for identically sized and similarly sited net energy metering (NEM) projects in California, interconnecting FOM projects costs significantly more, takes longer, and is far less predictable.
Project type |
Average utility charges per project |
Average timeframe |
Cost predictability |
NEM projects up to 1 MW |
$150 |
105 days |
Standardized flat fee |
FOM projects up to 1 MW |
$150,000 |
137 days |
Individual costs, estimated case by case, and subject to post-contract revision |
A significant roadblock for developers of FOM projects is the lack of predictability. Currently, for these projects it’s not possible to use publicly available information to determine impacts and costs prior to completing an application. The costs incurred prior to being able to submit an application vary widely, but they can typically exceed $50,000, with upgrades averaging $150,000 for a 1 MW project. This presents a major risk for developers.